OSS Cabinet Day: MEC Frazer Monitors Bailey Bridge Project in the EThekwini Municipality

The KwaZulu-Natal MEC for Education, Ms Mbali Frazer, together with the Department of Transport HOD, Mr Siboniso Mbhele, and officials from various spheres of Government, visited the Bailey Bridge Project called Mzinyathi L3105 as part of Operation Sukuma Sakhe Programme to monitor the progress of service delivery to the community of ward 3 in the EThekwini Municipality today, 06 March 2024.

The Bailey Bridge currently under construction in Mzinyathi area is part of the Government’s Welisizwe Rural Bridges Programme. This is a programme initiated by Government to ensure urgent construction of bridges and to eradicate the low lying water bridges that are making it difficult for people to cross from one area to another, especially during the rainy inclement weather.

Mzinyathi L3105 project started on 11 November 2022 and was due to be complete on 10 March 2023. The project encountered some delayed due to severe weather conditions and other financially related issues. The new completions date is 30 March 2025.

“I am happy that even though we have not met our initial completion target date, the project is 90% complete, and it is satisfying to see the collaboration of SANDF with community members in projects like these,” said MEC Frazer.

Mzinyathi L3105 Bailey Bridge is constructed by SADF and members of the community recruited through the Expanded Public Works Programme.

Venue: Mzinyathi L3105, in Ward 3, EThekwini Municipality

Date: 06 March 2024